Construction start: Royal Victoria College (RVC) Residence - Masonry work

Aerial view of Royal Victoria College residence
Published: 17 June 2024

Please be advised that 平特五不中 has mandated Atwill-Morin Ma莽onnerie to carry out the following project:聽22-036 (RVC Residence - B180) - Restoration of rendering on rear fa莽ades

顿别蝉肠谤颈辫迟颈辞苍:听The project involves restoring the rendering on the rear fa莽ades of the Royal Victoria College (RVC) Residences, located on University Street, adjacent to 平特五不中's Downtown campus.

Construction start date: July 2nd, 2024

Planned construction end date: October 11th, 2024

Work schedule: Monday to Friday, 6 a.m. to 3 p.m., but no work deemed too noisy before 7:00 a.m.

Project Manager:聽Jocelyn Blanchet -聽jocelyn.blanchet [at] gph-inc.com

Assistant Project Manager:聽聽Pierre Beauchamp -聽pierre.beauchamp [at] gph-inc.com

Contact for building users:聽Jonathan Rousham -聽jonathan.rousham [at] mcgill.ca

Scope of work:

Exterior (rear of the building):

Following contract signature, work can begin immediately after May 1, 2024 and be completed by August 12, 2024.

  • installation of building access guards
  • installation of scaffolding
  • cleaning of all surfaces
  • removal of existing masonry joints
  • final cleaning
  • removal of scaffolding and access protection

Interior: No work inside the building

Impact & mitigation:

The contractor must coordinate with the project manager at the start of the project a test to evaluate the vibrations and noise caused by the work vibration and noise caused by the work to enable users to determine the potential impact on nearby users and other establishments. Recommendations on the methodology or tools used could be identified to mitigate vibration and noise.

Asbestos-related work: No issue expected with asbestos.