ƽÌØÎå²»ÖÐ

News

Construction Start: Pulp & Paper - JELF OCT 2022, Von Sperber

Internal depiction of Pulp & Paper Building
Published: 29 October 2024

Please be advised that FMAS Operations, Southeast Sector, will carry out the following project: 22-029 PULP & PAPER - JELF OCT 2022, Von Sperber

¶Ù±ð²õ³¦°ù¾±±è³Ù¾±´Ç²Ô:ÌýTo carry out electrical works between Lab 202 and existing electrical panel in 2-Hall1

Construction start date: November 4, 2024.

Planned construction end date: November 30, 2024

Work schedule: Monday to Friday, 6 a.m. to 3 p.m., on a part-time basis

Project Manager and Assistant Project Manager: mona.modarressi [at] mcgill.ca (Mona Moudarressi) /Ìýrabih.farah [at] mcgill.ca (Rabih Farah)

Contact for building users:

Building Director – Chemistry: jean-marc.gauthier [at] mcgill.ca (Jean-Marc Gauthier)

--------------------------------------------------------------------------------------------------------

Scope of work:

The work consists

  • Installing new outlets in Lab 202
  • Installing new breakers in existing panel in 2-Hall1
  • Running conduits and cables between the new outlets and the existing panel
  • Performing an electrical shutdown (date to be communicated once determined)

Impact & mitigation:

  • Protection of the equipment, where needed, in the work zone
    • To be coordinated with the lab users and building administration
  • Works during the day on a part-time basis
    • To be coordinated with the lab users and building administration
  • Electrical shutdown:
    • To be coordinated with the lab users and building administration
    • Impacted staff will be informed in advance

Safety considerations:

Some drilling into materials containing silica is required to fix the new installations to the ceiling. Applicable safety protocols will be put in place, including dust-containment measures such as the use of specialized vacuuming equipment.

Back to top