平特五不中

News

McIntyre Renovations: Demolition on floors 8, 9 and 10

Published: 3 March 2010

Demolition of floors 8, 9 and 10聽 began March 3.

Material will be removed in the evening (after 5:00 pm) through elevator #59. You will notice the protections added inside the elevator. Containers will be placed on the West side of the entranceway (underneath the building extension). There will be no garbage chute installed as previously mentioned.

Schedule:

  • The contractor鈥檚 crew has mobilized and demolition operations have begun.
  • Demolition completion date: April 9, 2010.

All contractors on site will wear a badge to identify themselves as part of this project.

Through meetings and other communications the building occupants, Building Director and Fire Prevention Office have been made aware of this project.

Thank you for your cooperation.

Back to top